Maintenance of engineering control measures

Pages44-45
44
11. Maintenance of engineering control measures
11.1. General principles
11.1.1. Engineering control measures should be thoroughly examined and tested
at suitable or specified intervals to ensure that they are continuing to perform as
originally intended. The intervals and content of the thorough examination should be in
accordance with national laws or criteria specified in national or international standards
approved or recognised by the competent authority, and should be specified as part of
the control measures outlined in Chapter 6 (Operational control measures), taking into
account the extent of the risk in the event of failure of the control measure.
11.1.2. The results of each thorough examination and test should be compared
with the assessment of risks and control measures outlined in Chapter 6 (Operational
control measures). Any defects disclosed as a result of the examination or test should
be remedied as soon as possible or within such time as the examiner directs.
11.1.3. A suitable record of each thorough examination should be kept.
11.2. Local exhaust ventilation
11.2.1. As an example of the content of the thorough examination and test, the
examination and test for local exhaust ventilation (LEV) should provide correctly the
information listed below:
(a) name and address of the employer responsible for the plant;
(b) identification and location of the LEV plant, and the process and hazardous
chemicals concerned;
(c) date of last thorough examination and test;
(d) conditions at time of test: normal production or special conditions (e.g. maximum
use);
(e) information about the LEV plant which shows:
(i) its intended operating performance for controlling the hazardous chemicals;
(ii) whether the plant still achieves the same performance;
(iii) if not, the repairs required to achieve that performance;
(f) methods used to make judgements in respect of (e) (ii) and (e) (iii) above (e.g.
visual, pressure measurements, air flow measurements, dust lamp, air sampling,
filter integrity tests);
(g) date of examination and test:
(h) name, designation and employer of the person carrying out the examination and
test;
(i) signature or authentication of the person carrying out the examination and test;