Extensions of time and liquidated damages in construction contracts in England and Wales
Author | Daniel Brawn |
Position | Galadari and Associates, Dubai, United Arab Emirates |
Building projects often cost more and take longer than originally planned. Delays may occur for example because the contractor was working inefficiently, which is its own fault, or because the employer instructed additional work, for which the contractor will be entitled to additional payment. If delays impacted upon the critical path rather than merely taking up available float, such that the contractor failed to meet the contractual completion date (“Critical Delay”), the contract will generally entitle the contractor to an extension of time (“EOT”) to the completion date for delaying events which under the contract are the responsibility of the employer. The contractor may also be entitled to its loss and expense, for example in the form of additional preliminaries (that is, the fixed cost of setting up and running the site per week).
The building contract should provide that the employer may grant an EOT if Critical Delay occurs which is the responsibility of the employer. In practice, EOTs are granted on behalf of the employer by the architect or contract administrator acting impartially between the parties. The contract may also provide that, if Critical Delay occurs which is the responsibility of the contractor (“Culpable Delay”), the employer may claim liquidated and ascertained damages (“LADs”) from the contractor. Thus, if a delay occurs, the contractor may seek an EOT, both as a defence to a claim for LADs and because it hopes to receive additional payment.
This article examines the relationship between EOTs and LADs, using the JCT form of building contract as an example ( Joint Contracts Tribunal Limited, 2009 ). This form is commonly used in England, its provisions are typical and the principles apply to other forms of contract, although some are more prescriptive than others as to precisely how an EOT is to be assessed. It is not intended here to examine the relationship between EOTs and additional payment to the contractor, which is a function of the precise wording of the contract and the particular facts. Likewise, the focus is on the law of England and Wales, although some reliance is also placed on extra jurisdictional case law for illustrative purposes.
The relationship between EOTs and LADs is defined in the building contract and at common law. The first task is to examine the law in relation to each and then to examine the relationship between them.
The building contract regulates the relationship between the parties and apportions risk. It should list those events for which the contractor is entitled to an EOT if there is Critical Delay (“Relevant Events”), which will be at the employer's risk. Events that are not listed will be at the contractor's risk. The Relevant Events typically include: acts of default by the employer, such as failure to grant possession of the site by the start date and late provision of information; perfectly valid actions, such as instructing variations or additional work; and neutral events which the parties agree will be at the employer's risk, such as unforeseen ground conditions and exceptionally adverse weather. Relevant Events vary between different forms of contract and are often amended by special conditions. This article is not concerned with the nature of Relevant Events, but considers the legal position when a Relevant Event has occurred.
When a delay occurs, there is a three-stage process:
Whether a Relevant Event caused Critical Delay depends upon an analysis of the facts as presented. The parties should maintain accurate contemporary records of events on site. However, it is not clear how EOTs should be assessed when Relevant Events occur concurrently with Culpable Delay.
In
The decision in
If there are two concurrent causes of delay, one of which is a relevant event, and the other is not, then the contractor is entitled to an extension of time for the period of delay caused by the relevant event notwithstanding the concurrent effect of the other event.
This agreement formed the basis of Dyson J.'s decision. In
It is important to be clear as to what was decided in
The decision in
Subsequently, in the Scottish case of
Three years later, City Inn's appeal was rejected 9. In his leading judgment, Lord Osborne analysed existing case law and considered causation at length. He pointed out that “concurrent delaying events” could refer to a number of situations: events...
To continue reading
Request your trial