The effectiveness of time bar clauses following the high court in decision in Andrews v. Australia and New Zealand Banking Group
Author | Philip Davenport |
Position | University of New South Wales, Sydney, Australia |
In Australia, adjudication under the Building and Construction Industry Security of Payment Act 1999 (NSW)1 (“the NSW Act”), or equivalent legislation in Australia2, is a common way that disputed payment claims under commercial construction contracts are decided. Construction contracts often contain penalty clauses. In particular, time bar clauses have been used to impose a penalty upon contractors and subcontractors. The case most often cited in adjudications as authority for the effectiveness of time bar clauses is
The subcontractor argued that the time bar clause in the contract (clause 45) was rendered void by section 34 of the NSW Act4. McDougall J decided that the time bar in clause 45 was effective and was not inconsistent with the NSW Act. His Honour said:
Where John Goss wishes to claim an amount over and above the Contract Amount (for example, for a variation, or for delay or disruption costs), it is required, as a precondition of such a claim, to give notice under, and complying with the terms of, cl 45. It is obvious why a head contractor in Leighton's position might stipulate for such notice. Firstly, it will enable the claim to be investigated promptly (and, perhaps, before any work comprised in it is rebuilt, or built over). Secondly, it will enable Leighton to monitor its overall exposure to the subcontractor. Thirdly, it will enable Leighton to assess its own position
It is correct to say that cl 45 operates to bar claims if the notice provisions in it are not followed. But it does not follow that cl 45 is thereby inconsistent with the rights given under the Act, so as to attract the operation of one or other of the alternatives set out in s 34(2)5.
The effect of the time bar was that the subcontractor was not able to pursue a claim for in excess of $2 million. The claimant did not argue and the court did not appreciate that would offend against the penalty doctrine. Had the notice of claim been even one day late, the claimant would have been penalised to the extent of possibly $2 million.
Most major construction companies now have similar time bars in their construction contracts. In adjudication they invoke the time bars to avoid paying subcontractors what would otherwise be the subcontractors' entitlement. They also use the time bar (when the subcontractor has failed to claim an extension of time within the prescribed period) to enable them to recover liquidated damages for periods of delay that they have caused to the subcontractor.
One major contractor has general conditions of subcontract that provide that the subcontractor has no entitlement to an extension of time unless the subcontractor has given a written notice of claim within three business days after the event causing the delay first occurs. Those same general conditions provide that the subcontractor must comply with any direction of the contractor and if the subcontractor does not, before complying with the direction and within three business days of the direction, provide a written notice of a claim for additional payment and an extension of time, the subcontractor will not be entitled to any additional money or time for complying with the direction.
When the issue of a time bar arises in adjudication the respondent almost invariably cites the
However, following
Section 2 of this paper explains the penalty doctrine and the
It has long been the law in England and Australia that a provision in a contract that would impose a penalty on a party to the contract is unenforceable. This is the penalty doctrine. A leading authority on the penalty doctrine is
If the Sub-contractor fails to comply with any of the conditions of this Sub-contract, the Contractor reserves the right to withhold payment of any monies due or becoming due to the Sub-contractor.
The House of Lords held that paragraph 3 of clause 14 of the subcontract was a penalty.
Lord Salmon said:
Paragraph 3 [of clause 14] purports to confer much more on contractors than the law allows. According to the natural meaning of its language, it would enable contractors to suspend or withhold payment of very large sums of money due to the sub-contractors in the event of the sub-contractors committing some minor breach of contract causing only trivial damage in no way comparable to the amount owed to sub-contractors. The paragraph is, therefore, unenforceable since it provides for the extraction of a penalty9.
The penalty doctrine was the subject of the
The customers argued that these fees were a penalty and were therefore unenforceable. They argued that the fees were imposed upon or in default of the occurrence of stipulated events but were out of all proportion to the loss or damage which might have been sustained by the bank by reason of the occurrence of the events. The bank argued that since the fees were not charged for breach of contract, they could not be a penalty. The primary judge followed the NSW Court of Appeal decision in
The penalty doctrine is described in the
In general terms, a stipulation
The court used the term “stipulation” rather than “term” or “condition” of a contract. The court did not change the penalty doctrine. It merely enunciated what the common law of Australia is. The court considered
In the
To continue reading
Request your trial