Cost benefit analysis approach to global claims
Author | Wayne Edward Lord |
Position | Department of Civil and Building Engineering, Loughborough University, Loughborough, UK |
This paper uses traditional doctrinal legal methodology to evaluate judicial statements on global claims, drawing on key authorities from a number of jurisdictions and from the realms of health and safety law and professional negligence. The purpose of this paper is to examine relevant case law governing the failure and/or success of global or rolled-up claims. It proposes a theoretical framework to improve a claimant's prospect of success in advancing a global claim, not only in circumstances where it may be impractical or impossible to provide a breakdown but also where a cost benefit analysis concludes it is logical and reasonable to do so. Global claims, if advanced correctly, could significantly reduce the costs of litigating complex construction disputes.
The general rule as regards a claimant being compensated in damages for breach of contract was set out by Lord Blackburn in these terms:
[…] in settling the sum of money to be given for reparation of damages you should as nearly as possible get at that sum of money which will put the party who has been injured, or who has suffered, in the same position as he would have been in if he has not sustained the wrong1.
In other words, the wronged party, so far as money can do it, should be placed in the same position as if the contract had been performed.
Contractors may find themselves in the position of having suffered a loss on a particular project and consider the whole of that loss is attributable to breaches of contract by the client. Contractors may then proceed, in a seemingly generalised and simplistic way, to present a claim for the total “loss” as a measure of damage which should compensate them for the harm suffered.
The claimant's right to be compensated for harm done should also be balanced up with the rights of the defendant as set out by Lord Justice Saville:
The basic purpose of pleadings is to enable the opposing party to know what case is being made in sufficient detail to enable that party properly to prepare to answer it2.
Global or “rolled-up claims” occur when the claimant presents a claim with no breakdown in the sense that, rather than showing how each individual event has caused delay together with the monetary loss attached to each delay, the claimant provides a single claim lumping each alleged cause together without itemisation. Such an approach under normal circumstances:
[…] is the antithesis of a claim where the causal nexus between the wrongful act or omission of the defendant and the loss of the plaintiff has been clearly and intelligibly pleaded3.
Lord Humphrey LLoyd QC also went on to say:
However, that nexus need not always be expressed since it may be inferred. As Lord Oliver emphasised in Wharf Properties there must be a discernable nexus between the wrong alleged and the consequent delay (or money) for otherwise there will be no “agenda” for the trial3.
Awards given on a global basis have been supported in the context of:
[…] an extremely complex interaction […] [where] it may be
The arbitrator in
[…] a rolled up award can only be made in a case where the loss or expense attributable to each head of claim cannot in reality be separated and […] where apart from that
Awards made by both arbitrators and adjudicators on a global basis have been supported by the courts4,6. There have, however, been notable failures. An argument commonly cited against the global approach is that it amounts to an abuse of process, such an argument usually being presented at an interlocutory stage in the form of an application to strike out the claim. The abuse can be categorised as where the claimant provides no particularisation to a claim such that the defendant does not know what he is defending himself against. In
It will be necessary at trial to consider all variations instructed in order to establish which of them are unnecessary7.
The court then concluded:
The failure even to attempt to specify any discernable nexus between the wrong alleged and the consequent delay provides, to use Mr Thomas's phrase [counsel for the defendants] “no agenda for the trial”7.
While Wharf could be argued to be the low point for global claims, in
Where however a claim is made for extra costs incurred through a delay as a result of various events whose consequences have a complex interaction that renders specific relation between event and time/money consequence
From Wharf onwards, we can see the courts reluctance to strike out global claims purely because they were presented as global claims.
The District Court of Western Australia (2007) defines the nature of a Scott schedule as being a form of pleading which allows the court to have before it a single document. That document conveniently providing a full description of each element of claim together with the adopted positions of each party (in terms of admission or denial and quantum/evidence) to each element. In
The objectives sought to be achieved by the Court in orders made relating to Scott Schedules are to ensure that when the action is entered for trial: each individual item claimed is particularised […] the amount asserted by both parties […] the contentions of each parties […] areas of agreement relating to the description of the item and quantum […] the aggregate of the claims and areas of admissions of each party are known9.
The claim in
Consideration was given as to how far the claimant must go in particularising his claim in the case of
What is
The Court of Appeal concluded that the core dispute, over pleadings and case management, in
Lord Woolf and Lord Justice Otton heard an appeal against the refusal of a late strikeout application of a poorly pleaded global claim in the case of
There are warnings against the danger of a global claim failing completely if any significant part of the delay is not established and the court finds no basis for awarding less than the whole ( Keating, 2006 ).
In
To continue reading
Request your trial